Larry Drive at Hubbard Drive in Heath is open again, restoring access to businesses along the corridor during the final phase of road construction.

The city of Heath announced the reopening Sunday, Nov. 22, naming Hawk Donuts, Pablo's Restaurant & Cantina and Heath Salon And Spa as businesses now easier to reach. The intersection had been closed for construction work on the Hubbard Drive Improvement Project, though the city did not specify when the most recent closure began.

The reopening comes as the fourth and final phase of the project continues toward a December 2026 completion deadline.

What the project covers

The final phase is reconstructing Hubbard Drive from Michael Lane to Smirl/Bois d'Arc Road. The work includes full pavement removal and replacement with concrete paving, new curbs and gutters, upgraded stormwater drainage and completion of a multi-use trail. Utility lines that conflict with the new road are being relocated.

The contractor is Apple Paving. Before construction began in early December 2025, the Heath City Council awarded the bid at a specially called meeting, according to the city's project page. The bid came in under budget at $5.4 million, with the city citing potential savings of more than $2.16 million.

The project was expected to take about 12 months from its December 2025 start. As of the city's updates, the work remained on schedule within the contract period ending in December 2026. The city noted that frequent rain had affected construction but that work continued.

City staff have been meeting weekly with Apple Paving. Residents can sign up for text updates by texting "HEATH" to 91896.